WorkerSense® Daily Site Report: Lockwood Builders, September 4th, 2018, Los Angeles, CA.
‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ 
alt_text
alt_text
alt_text

September 4th, 2018

Evening, Daniel. Today, we monitored 42 workers for a total of 327.6 man hours. On average, your workforce arrived on site at 7:41 am, and left at 3:29 pm, performing at a 93.2% rating, with a 76.3% distribution. No safety risks were observed.

alt_text

Workforce Insights

Fresno Electric was the earliest-arriving contractor, on average clocking in at 7:14 am. Blue HVAC Systems was the last contractor to arrive, coming on site at 8:05 am.California Drywall was the busiest contractor, with an average shift length of 9.3 hours.

For detailed timecard data for each worker, see the attached .CSV file.

alt_text

The above plot shows site personnel volume, and worker activity timing. Click on the plot for an interactive version.

Performance Insights

Temperatures were fairly high on site today, impacting the performance of your workforce. Daily temperatures maxed out around 12:11 PM, hitting 87°F. Relative humidity was less impactful, reaching a daily maximum of only 75%. Your workforce's overall performance and work distribution both begin to decline as temperatures rise. Continue to provide your workforce with hydration and cooling breaks to combat this.

For detailed exposure and performance data for each worker, see the attached .CSV file.

alt_text

The above plot shows average site temperature, average site performance rating, and average site work distribution. Click on the plot for an interactive version.

alt_text

Efficiency Insights

Total operational efficiencies were higher than average today. Of the sources below, performance decline was responsible for the majority of time lost per worker, averaging 32.6 minutes. In total, addressable operational inefficiencies were responsible for 67.41 lost production hours site-wide, or $976.77 in labor expenses.

For detailed inefficiency data for each worker, see the attached .CSV file.

alt_text

The above plot shows average work start delay, work end delay, unscheduled break time, and performance decline. Click on the plot for an interactive version.

alt_text

Area of Work Insights

Your workforce covered 1.2 square miles today, each worker traveling an average of 0.9 miles. A heatmap visualizing areas of work is below.

For detailed movement data for each worker, see the attached .CSV file.

alt_text

The above map shows the distribution of work on site. Click on the map for a high resolution version.

That''s all for today. Continue to keep an eye out for SMS alerts regarding performance and safety, and check out WorkerSpot for real-time site information.







WorkerSense, Inc
555 W 5th St, 35th Floor, Los Angeles, CA, 90013 US